Tower Decommissioning Project in Lincolnshire

 

We recently found ourselves over 100m above the ground with breathtaking views across the countryside as we set about a tower decommissioning project in Lincolnshire.

Located close to the village of Mablethorpe, the tower was home to a number of dishes which were no longer required. Our job was to remove the dishes, plus all feeder cable and ancillary equipment. No mean feat when you consider that the eight dishes measure over 3.5m across and are located between 122m and 145m up the tower.

Dish Removal

Before any work could start, we had to gain access to the site, evaluate the site and perform a pre-work survey and carry out a risk assessment. We were also required to set up a Safety Exclusion Zone around the work area, which took into account the height of the work being undertaken – signage and barriers were put up where required.

Due to the height of the dishes, an anemometer was set up at working height level so we could check to see if the wind speed was within the permitted parameters to allow work to commence.

As some of the works were more weather dependent than others, priority was given to weather dependent tasks, prioritized as follows:

Priority 1          Removal of dishes at high level

Priority 2          Removal of small antenna & removal of high-level redundant feeder and wave guides

Priority 3          Removal of low-level redundant feeder and wave guides

Priority 4          Cutting up and removal of decommissioned equipment at ground level

A trailer winch was used to remove the dishes, where the winch, bond and pulley blocks were all rated with an SWL suitable for the lift. A pilot line / tight line was hoisted up using the winch and set above the antenna. This was subsequently attached to the appropriate anchor point at ground level.

We then ascended the tower and set up the winch bond on a pulley block above the proposed lift. The load was secured to the pilot line with a sling and winch, as well as to the winch bond. The winch was used to take the weight of the dish to be removed, before the team carefully unbolted and released the dish. This was lowered to the ground using the winch. This process was repeated for the other four large dishes.

Small Antenna Removal

The small antennae were removed using either the trailer winch or the 300m rope and capstan winch. Like the larger dishes, the antennae were secured to the lifting system and unbolted from the structure, before being lowered to the ground in a controlled manner for disposal from the site.

Feeder and Waveguide Removal

For the feeder and waveguide removal, the 300m rope and capstan winch was used. Section of feeder were secured before the fixings were removed and placed in a bolt bag or lifting bag. Manageable sections of feeder were cut off and lowered to the ground for disposal from the site.

Disposal of Equipment

Decommissioned equipment was cut up and taken from the site by licenced waste carriers to a licenced waste disposal specialist.

On completion of the works, all materials and rubbish were removed from the site, and the site was left in a clean and tidy state, approved by the client.

The LARS Team

All LARS staff working on this tower decommissioning project in Lincolnshire undertake regular training for all aspects of their works. They are highly trained in rooftop and tower climbing, tower rescue, RF awareness and emergency first aid; they will also carry valid documentation.

They will be wearing PPE consisting of a full body harness (where required) and helmet. When ascending the structure, LARS staff will remain attached to it at all times. Helmets will be worn at all times when operatives are working on the structure.

For more information about our range of services, please click here.