We have recently returned from the Isle of Wight where we were carrying out a challenging tower installation.
The project was carried out in conjunction with Royal Haskoning on behalf of the UK’s Maritime and Coastguard Agency. And although the tower itself was relatively small, standing at 12.5 metres, the size of the challenge for the team was anything but small, due to its location.
The tower stands on West High Down, overlooking the famous Needles landmark, meaning access was far from straightforward. In fact, due to the limited access, the 12.5m tower was manufactured in 3m sections and built using a lifting derrick rather than a crane.
Full Turnkey Solution
This installation on the Isle of Wight is another of a full turnkey solution. The task begun with the submission of detailed tower designs, once again carried out by our design partners, Hampshire-based MFD Communication Infrastructure Limited.
Upon approval of the designs, the tower was fabricated in 3m section in our in-house fabrication workshop and subsequently transported to the location.
Before the installation could begin, the existing structure and its foundations were decommissioned and disposed of responsibly, complying with all environmental regulations – we carry a waste licence from the Environmental Agency and our Environmental Management System is compliant with the requirements of ISO 14001.
The installation included the excavation of the grounds to allow for the provision of a new reinforced concrete foundation. Once in place, the tower was installed, complete with ladder, fall-arrest system and all the plates, bolts, brackets and feeder cable required for the antennas which will be rigged to the tower.
The final requirement was to reinstate the grounds. Given the location and the popularity of the area, it was important that we left the area looking as it did when we arrived. This meant reinstating turf, seeding grass where required and landscaping – we had laid trackway / flooring to protect the grounds as much as possible during the course of the works.
Can-do Company
This is certainly not the first challenging operation we’ve undertaken – in fact, we’ve developed a reputation for rising to the challenge. It’s quite often that a customer will get in touch with us because they know we’re a can-do company, and this tower installation on the Isle of Wight was no different. On paper it seems simple enough, but once you’ve had access to the location, you soon realise the size of the task facing you.
But once again the team has done an amazing job, delivering the tower on time and on budget, despite all the challenges facing them.