Tower Installation in Northumberland

We have recently returned from Colliersdene Plantation, a forest in Northumberland, where our teams were installing a lattice tower on behalf of AXD Special Projects.

AXD Special Projects Limited was founded in 2019 to construct and manage specialist projects across a number of sectors including telecommunications, utilities, broadcast and power generation.

Tower Installation Procedure

The tower was delivered in five galvanized steel sections – sections A and £ were flatpacked (to be assembled on-site), while sections B, C and D arrived already assembled.

All tower sections were delivered on a suitable wagon which was sited in such a position as outlined within the separate crane lift plan. All lifting equipment used for unloading complied with current LOLER certification and was specified for a suitable Safe Working Load (SWL).

Due to the nature of the incomplete structure, qualified rigging climbers were necessary, able to ascend the tower ‘off ladder’. Our riggers safely used the erected steelwork structure, main leg and infill members to climb to the required positions needed to secure the next section. They also remained attached to the secure steelwork at all times.

The tower was assembled section by section, our operatives ascending the tower to the point where the new section was to be located. As each section was carefully lowered into place, our team lined up the holes in the flange plates using podger spanners and then fitted the bolts. During the course of the exercise, wherever possible the rigger remained inside the structure, clipped into a safe working position.

On completion of the tower erection, all fixings and bolts were re-checked for tightness and the verticality of the structure was also checked where necessary before we issued a safe to climb certificate.

Our Climbing Operatives

All of our climbing operatives have undertaken the following training and assessment and hold current valid certification as follows:

  • Tower Climb and Rescue (To MATS Standard)
  • Roof Top Worker (To MATS Standard)
  • RF Awareness (To MATS Standard)
  • First Aid at Height
  • Working at Height Medical

The site was run in a clean and tidy manner; all waste materials were tidied as the works progressed (where practically possible) and removed from site on the completion of works.

Senior Contracts Manager at AXD Special Projects, Jonathan Harrison, was very happy with the outcome, saying; “As always a great job completed by the LARS team, on time, on schedule and on budget.”