Tower Strengthening Project in Wiltshire

We are pleased to announce the successful completion of a comprehensive tower strengthening project in Wiltshire, carried out for MFD Communications Infrastructure on behalf of the Wireless Infrastructure Group. The project, which involved both extensive ground works and structural reinforcement, demonstrates our commitment to maintaining and upgrading critical telecommunications infrastructure.

Project overview

The scope of works included comprehensive groundworks to prepare the site for the tower strengthening, followed by the tower remedial works, designed to ensure the long-term stability and reliability of the structure.

Tower strengthening in Wiltshire

Phase 1: Groundworks

Our team began by preparing the ground for the subsequent tower strengthening works. This involved:

  • Concrete Plinth Breakout and Reinstatement: Existing concrete plinths around each tower leg were carefully removed using hand breakers. Concrete was chiselled away from the tower members to allow for the loosening and replacement of each member. New concrete shutters were then erected and a concrete mix was poured and levelled to create new base plinths to the customer’s specifications. After sufficient curing time, the shutters were removed.
  • Earth Tape Installation: Surface mounted earth tapes were run to each tower leg, reinstating the existing earth tape where possible, or installing new tapes where necessary.
  • Site Clearance: All broken concrete and redundant materials were removed from the site and transported back to LARS in company vehicles, ensuring a clean and tidy work environment.

Phase 2: Tower Strengthening

With the groundworks in place, we embarked on the tower strengthening works, which involved remedial bracket works at 10 metres under the platform. Key aspects of the operation included:

  • Two experienced and fully trained climbers accessed the platform and removed flooring clips to safely lift out the grillage flooring panels.
  • Linesman ladders were lifted and secured, enabling safe access for climbers to clean and paint the brackets.
  • The flooring panels were reinstated and secured upon completion of the maintenance work.

Further strengthening involved the replacement of existing steel members. This process included:

  1. Reviewing site documentation and adhering to MFDCI procedures.
  2. Installing scaffolding to ensure safe access and prevent encroachment on power lines.
  3. Checking wind conditions before disconnecting existing members.
  4. Using a rope system and scaffold to safely remove and replace steel members.
  5. Preparing and painting new steel sections before installation.
  6. Use of a capstan winch to lift and secure new steel into place.
  7. Ensuring all bolts were properly tightened and securing additional access where required.
  8. Documenting the process with photographs for the final handover pack.
  9. Conducting a final site cleanup to leave the area in pristine condition.

Commitment to Safety

Throughout the project, safety was a top priority. We ensured that all operatives complied with stringent safety regulations. Personal Protective Equipment (PPE) was worn at all times, including safety boots, helmets, high-visibility clothing, safety harnesses, gloves, and goggles. Each team member was fully trained in rooftop and tower climbing, tower rescue, RF awareness and emergency first aid.

Project Completion

We take great pride in delivering high-quality infrastructure solutions while maintaining a strong focus on safety and efficiency. With the successful completion of tower strengthening project in Wiltshire, we continue to demonstrate our expertise in tower strengthening and groundworks, supporting critical communication networks across the UK.

The upgraded tower now stands ready to continue its vital role in supporting wireless communications infrastructure in the Wiltshire region.

For more information on our services please click here.