We have recently completed a significant tower extension project at the Denton Wharf facility, part of the Port of London Authority (PLA). The project involved the careful removal of an existing tower section and headframe, followed by the installation of a new, taller structure to enhance functionality and access for essential equipment.
About the tower
The Denton Tower, originally an 18m steel lattice structure, has now been extended to 31m. Constructed using tubular legs and angular bracings, the tower provides critical infrastructure for the PLA.
To maintain operational efficiency, existing equipment has been relocated at the same heights on the tower. The upgrade also includes additional horizontal members for improved accessibility and a platform positioned 2m below the top of the tower to enhance functionality. This platform will serve as a strategic access point for the numerous equipment installations at the top the tower, ensuring convenient and safe servicing and maintenance procedures.
Delivery and preparation
The delivery phase saw the arrival of the steelwork and tower sections at the designated work area. The grillage sections were strategically positioned on wooden shocks, ready for pick up when needed. The tower sections were carefully sorted and prepared for the next phase.
Assembly
The assembly process involved building the lower 5-meter tower sections horizontally on the ground. Using a crane, the upper leg was lifted to complete the assembly. Ladder sections and lightning finials were then bolted into place. The assembled sections were laid out, ready for the crane to pick up and position.
Removal of redundant components
Before the removal of the old tower section, the existing camera was carefully taken down by the rigging team. It was then handed over to the PLA for reinstallation later.
The removal process was then carried out by a rigger and a slinger banksman. They ascended to the tower’s top, slinging the headframe and unbolting it for the crane to lift it clear. The same process was repeated for the tower section. Once on the ground, the steelwork was dismantled and loaded onto a lorry for removal.
Installation of new tower section
The newly fabricated tower sections were lifted into place using a crane, either individually or pre-bolted into longer sections. Riggers ensured precise alignment before securing the sections with bolts. Each newly installed section was inspected for proper fastening, and once the entire structure was in place, final tightening checks were conducted using hand and battery-operated tools.
To enhance safety, we also installed a Latchway fall arrest system using a pulley system, followed by a thorough safety inspection and the placement of a ‘safe to climb’ placard.
Completion and Final Inspection
Upon completing the tower extension, a full structural and safety inspection was conducted. A Latchway and ‘safe to climb’ certificate was issued, verifying the integrity of the installation. Finally, all surplus materials were removed and the site made clean and tidy.
Commitment to Safety
All climbing operatives involved in the project were highly trained and held current certifications, including:
- Tower Climb and Rescue (MATS Standard)
- Roof Top Worker (MATS Standard)
- RF Awareness (MATS Standard)
- First Aid at Height
- Working at Height Medical
The successful tower extension at Denton Wharf underscores our commitment to delivering high-quality, safe and efficient tower infrastructure solutions. By ensuring a seamless transition from the old structure to the new, we continue to play a pivotal role in supporting the operational needs of the Port of London Authority.