We have recently returned from East Sussex where we were carrying out a tower strengthening job on behalf of our client, Hampshire-based MFDCI.
OVERVIEW
LARS was responsible for installing additional support to five sections of the 60m tower.
CLIMBING OPERATIVES
All climbing operatives shall have undertaken the following training and assessment and hold current valid certification follows:
- Tower Climb and Rescue (To MATS Standard)
- Roof Top Worker (To MATS Standard)
- RF Awareness (To MATS Standard)
- First Aid at Height
- Working at Height Medical
Location:
East Sussex
Sector:
Emergency Services
Service:
Tower Strengthening and Structural Upgrades
- Site documentation will be reviewed prior to the start of works including this method statement
- The team leader will ensure safe methods of working are followed
- The engineers will then establish and mark drop zone using warning signs, barrier tape or barriers if available, deploy rescue kit at the base of the tower
- Carry out RF survey of work area
- LARS operatives will ascend the tower to the required height’s using approved climbing methods and appropriate fall arrest systems, second engineers will remain on the ground. If no fixed fall arrest is available then the double lanyard method will be used to ensure engineer is attached at all times
- For access to the tower locations the site Team leader may use a hook on Aluminium ladder to aid access to parts of the tower not easily accessible
- Installation of additional redundant plan bracing members (50x50x6) between 0.3m and 3.0m
- Installation of additional redundant plan bracing members (50x50x6) between 3.0m and 6.0m
- Installation of additional redundant plan and hip bracing members (50x50x6) between 21.0m and 24.0m
- Installation of additional hip bracing members (50x50x6) between 27.0m amd 30.0m
- Installation of additional redundant plan bracing members (50x50x6) between 30.0m and 33.0m
- All new steelwork hot dip galvanised to BS EN 1461
- New hole locations will be measured and marked
- Holes will be drilled to correct size in accordance with drawings
- Drilled holes will be deburred and cut surfaces painted with Galvafroid paint
- New members will be bolted into position
- Bolt tightness will be checked
- Photographs will be taken for handover pack
- Site will be left clean and tidy
Outcome
The tower strengthening works were completed on time and on budget. The tower remains fir for purpose and has been issued with a ‘Safe to Climb’ certificate.