LARS is proud to announce the successful completion of a complex decommissioning project in Lincolnshire.
Overview
The project involved the controlled demolition of a 135-metre triangular guyed mast structure which had been in operation since 1991. LARS worked collaboratively with ecological consultants and demolition specialists to ensure minimal environmental impact and maximum safety. All phases of the project, from pre-demolition planning to post-demolition site clearance, were completed without incident, underscoring LARS’ capability in carrying out complex decommissioning projects.
Location:
Lincolnshire
Sector:
Communications
Service:
Radio Site Decommissioning
Decommissioning of Structure
- PHASE 1: PRE-DEMOLITION PREPARATION
- Ecological survey: Ecologist carried out a survey to identify any potential wildlife implications and implement necessary mitigation measures
- Service checks: Comprehensive search undertaken to identify and protect any underground services that could be damaged by the falling structure
- Site clearance: Undergrowth was cut back from the mast's demolition area, guy anchor and guy wire locations. This step was subject to the ecologist's report, aiming to remove habitat and improve safe access
- Permissions and notifications: Demolition permits secured from local authorities and permissions obtained from adjacent landowners to ensure access and to set up the works cordon
- PHASE 2: SITE SETUP (1-2 DAYS PRIOR TO DEMOLITION)
- Equipment delivery: LARS delivered critical site infrastructure including Heras fencing, sandbags, fire extinguishers, pallets and a mobile welfare unit
- Pre-demolition removals: Gantry fencing removed (leaving the aircraft lighting cable in place) and chain link fencing was removed in the direction of the fall
- PHASE 3: DEMOLITION DAY
- Plant arrival: 13-tonne excavator with demolition shears / grab; tracked dumper; scrap skip; and HIAB lorry for scrap removal
- Explosives preparation: Charges prepared and placed on the south-east guy lane anchors, using pallets and sandbags for blast control
- Safety cordon established: A robust safety cordon was set up with an 250m radius, manned by eight marshals equipped with radios for continuous communication
- Area clearance confirmation: The cordoned-off area was thoroughly walked and swept to ensure no wildlife or personnel were present. A drone was used to assist in confirming the area's clear status
- Communication check: All communication channels with the cordon marshals were verified
- Demolition sequence: The countdown commenced and the siren warning was sounded. The charges were then fired leading to the controlled collapse of the mast in the Northwest direction
- PHASE 4: POST-DEMOLITION CLEAN-UP
- Safety inspection: The collapsed structure was thoroughly examined with any parts appearing to be dangerous made safe as a priority using demolition shears
- Structure clearance: Debris was cut and sorted according to priority and any parts which crossed the field access or drainage ditches were cut and brought back into the compound
- Resecuring the site: Site was made safe using Heras fencing
- PHASE 5: FINAL SITE CLEARANCE
- Material removal: Remaining mast components were moved via dumper for loading onto lorries and removed from the site – small items were placed into skips
- Site restoration: The compound fence was fully reinstated and a final sweep was undertaken before all plant, equipment and welfare facilities were removed and the site was locked up
OUTCOME
This successful decommissioning project demonstrates LARS’ ability to manage complex structural demolitions with precision and care. Through diligent planning, stakeholder collaboration and a strong emphasis on safety and the environment, the mast was dismantled efficiently with no incidents and minimal disruption to the surrounding environment.
For more information about our decommissioning services, please click here.