LARS has completed the design, fabrication and installation of a RADAR tower in South Wales.
Overview
LARS was the principal contractor on the project, responsible for the design, build and installation of this RADAR tower in South Wales, as well as the manufacture and installation of the tower cabin which houses all electrical components.
Tower Design, Build and Installation
The new tower, designed to support the radar array and radar cabin, is a bespoke design, developed and applied to various sites across the UK. This version in South Wales is one of the 20m versions of the design, and the most recent to be completed as part of an ongoing contract.
The four-leg angle structure is constructed in 5m sections, including an internal staircase and working platform on all four sides at the top of the tower. The top section also supports the radar cabin where all the electrical components are housed. All steelwork fabrication and construction are carried out in LARS’ in-house fabrication workshop in Carnforth, Lancashire.
Once the tower has been transported to the site, LARS oversees all plant equipment for the installation, including cranes, telehandlers, traffic management systems and task lighting. LARS’ experienced climbing teams undertake the installation of the structure.
Tower Installation Sequence – Lower Section One
Attach the 2 legs of the tower onto the assembly grillage (or direct to base) and attach horizontal and diagonal bracing between these legs.
Attach the 2 legs of the tower to the opposite face and attach the horizontal and diagonal braces from the first section.
Install the lower flight of stairs, grillage and hand railing to cross member.
Install the upper flight of stairs. These will require temporary sling to hold in approx. position.
Install cable management support.
Carry out bolt check to ensure the bolt are installed correctly but not tightened fully.
Lift section onto base, with crane, if assembled on assembly grillage.
Tower Installation Sequence – Tower Section Two
Repeat as per section 1 for each section but installing onto template grillage until tower has been completed. MEWPs/scaffolding or climbers may be utilised for the connection of each leg section to the next. A separate set of RAMS will be supplied and included within the construction file if required.
Once the section has been assembled the crane to be attached to the centre of each face to ensure
horizontal level is maintained and then the section can be lifted into place.
With a rigger positioned diagonally opposite each in attached to the tower leg of the lower section,
the next section to be guided into position and bolted down. The riggers will then relocate to the other legs and install the required bolts.
After each level has been installed the level should be verified. At this point the bolts shall be nipped
but not tightened. This will enable the next section to be landed and levelled.
On completion of the upper level, return to the section below and tighten to the correct Nm² as per
the specification.
The Radar Cabin
Designed and developed at the LARS Carnforth depot, the RADAR cabin was assembled away from the build area to allow cladding to be applied to the cabin and ensuring this element doesn’t interfere with the progress of the tower build.
As soon as the work on the upper section of the tower began, the cabin was moved closer to the tower build area to allow installation. Once the cabin had been installed on the tower, all wall mounted components were fixed, and the final section of the tower was lifted into place and secured.
On completion of the cabin install the client will be invited to fix any wall mounted components (see contractor rams). Once secured into the cabin the crane will lift the section as secure to previous section. All bolts will then be tightened to correct Nm² torque as per specification.
The Anti-climb panels will be bolted around the stairs. These will be fixed to the base using resin anchors. The gantry poles will be fixed to the concrete base and the cable gantry bolted in place. Cable basket will be fitted and the ice guard attached.
Scope of works:
Location:
South Wales
Sector:
Defence
Service:
Design, Fabrication and Installation of Structures
- Crane lifting: undertake crane survey and agree on lift plan
- Deliver case in grillage and stubs to civil contractor on site so they can be case in to the concrete foundations
- Delivery of tower and RADAR cabin on lorry. Employ traffic management company to install traffic light system adjacent to the site, allowing lorries to be unloaded safely and allow for temporary suspension of traffic during lifting operations
- Agree tower erection sequence ensuring appropriate mechanical assistance. Use of a crane for lifting the bundles and assembled faces
- Assembly and erection of 20m RADAR tower (in sections), RADAR cabin (away from build area), access staircase to platform level (including handrails and non-slip treads)
- Cladding of RADAR cabin
- Installation of RADAR cabin and fixing of all wall-mounted components as required
- Supply fit and fix lightning protection for RADAR tower
- Anti-climb panels bolted around the stairs, fixed to the base using resin anchors
- Gantry poles fixed to concrete base and cable gantry bolted in place
- Once all sections are installed carry out 100% bolt check ensuring each bolt is tightened to required Nm²
- On completion of all works, the site was cleared of all materials and waste and the site left in a clean and tidy condition
Outcome
This radar tower in South Wales was a 20m version of the bespoke radar tower and cabin design. From the initial designs to the decommissioning and the final installation, the radar tower project has run smoothly, with all elements completed within the allotted time frame and on budget.