Radar Tower in the South of England

LARS has completed the design, fabrication and installation of a RADAR tower and cabin in the South of England.

Overview

LARS Communications was the principal contractor on this radar tower project, responsible for the design, build and installation of the new 35m tower, as well as the manufacture and installation of the cabin which houses all electrical components.

Tower Design, Build and Installation

The new tower, designed to support the radar array and cabin, is a brand new, bespoke design, developed and applied to various sites across the UK. This radar tower in the South of England is the first 35m version of the design.

The four-leg angle structure is constructed in 5m sections, including an internal staircase and working platform on all four sides at the top of the tower. The top section also supports the RADAR cabin where all the electrical components are housed. All steelwork fabrication and construction are carried out in LARS’ in-house fabrication workshop in Carnforth, Lancashire.

Once the tower has been transported to the site, LARS oversees all plant equipment for the installation, including cranes, telehandlers, traffic management systems and task lighting. LARS’ experienced climbing teams undertake the installation of the structure.

The Cabin

Designed and developed at the LARS Carnforth depot, the cabin was assembled away from the build area to allow it to be cladded and so not hold up the progress of the tower build.

Once the work on the upper section of the tower begins, the cabin was moved closer to the tower build area to allow installation. Once the cabin had been installed, all wall mounted components were fixed, and the final section of the tower was lifted into place and secured.

Scope of works:

Location:

The South of England

Sector:

Aviation

Service:

Fabrication and Installation of Structures

Outcome

This was the first 35m iteration of the bespoke RADAR tower and cabin design, a project that has been really exciting for everyone involved. From the initial designs to the final installation, the teams involved have been fantastic, completing the project within the allotted time frame and on budget.