Tower Installation – Isle of Wight

LARS has completed the design, fabrication and installation of a 12.5m tower on West High Down, overlooking the famous Needles landmark on the Isle of Wight.

Overview

Working in conjunction with Royal Haskoning on behalf of the UK’s Maritime and Coastguard Agency (MCA), LARS Communications was responsible for the design, build and installation of a new 12.5m tower on West High Down on the Isle of Wight.

Full Turnkey Solution

The new tower was designed by LARS’ design partners, MFDCI Limited, and, upon approval of the designs, was built-in 3m sections in LARS’ in-house fabrication workshop in Carnforth.

Prior to the installation, the existing structure and its foundations required decommissioning and disposing of responsibly, complying with all environmental regulations.

The installation included the excavation of the grounds to allow for the provision of a new reinforced concrete foundation.

The final requirement was to reinstate the grounds. Given the location and the popularity of the area, it was important that we left the area looking as it did prior to our arrival.

Structure Build Process

Due to the difficult access to site the tower was manufactured in 3m sections and was built using a lifting derrick, rather than a crane. The tower sections were brought to the site in component form. The ladder sections and feeder brackets were also brought to the site loose.

  • The lower leg sections, will be stood up manually and bolted on to the base flanges, which protrude from the base.
  • Working from the bottom up, the infill braces will be bolted into the face of the tower, these will be climbed as required when moving upwards.
  • Once the lower 3m section is built the aluminium lifting derrick will be fitted to one of the upright tower legs.
  • Using the derrick the 3 leg sections for the next section of tower will be hoisted into position and bolted in place.
  • Working from the bottom up, the infill braces will be bolted into the face of the tower, these will be climbed as required when moving upwards.
  • This process will be repeated until all 4 levels of the tower are built.
  • Once the tower the ladder will be hoisted into position and bolted in place.
  • On completion all bolts will be checked and marked.

Once in place, our qualified team installed the latchway system and rigged the structure (antennas provided by MCA).

On completion of the works, the MCA representatives were invited to site to check and transfer the transmission from the old mast to the new mast, to allow decommissioning of the old mast.

Existing Structure Removal

  • Safety cordon will be set up
  • Riggers to ensure that all the existing equipment is isolated / disconnected.
  • Abacus lifting and lowering unit will be hired to lower the redundant monopole
  • The unit will be attached and following the supplier/manufacturers instruction the monopole will be lowered to the horizontal
  • Once in the horizontal, the monopole will be cut up into manageable sections with grinder, removed from the work area and placed in a metal skip for removal from site.

Existing Base Removal

  • Using a 2T excavator with a hydraulic braker the existing base will be broken out.
  • Broken concrete will be loaded into wheelbarrows and transferred to a skip for removal from site
  • Surplus spoil from the excavation, will be graded into the excavation and made good.

Scope of works:

Location:

West High Down, Isle of Wight

Sector:

Maritime

Service:

Design, Fabrication and Installation of Structures

Outcome

This project was undertaken in conjunction with Royal Haskoning. Despite the challenge of the location, the team worked diligently and collaboratively, delivering the project smoothly, on time and on budget.

For more information about our range of services, please visit our Services Page.

General enquiries or to arrange an appointment…